✅ Correct Answer: B. Split sprint capacity between debt and feature work
🔍 Explanation
A. Defer debt; build the feature
❌ Sacrifices long‑term health. Ignored debt compounds, slows velocity, and raises risk.
B. Split sprint capacity
✅ Reserves planned bandwidth for technical‑debt reduction and delivers customer value, supporting sustainable pace and product quality.
C. Ask team to work overtime
❌ Violates Agile’s sustainable‑pace principle; overtime invites burnout and defects.
D. Escalate to senior management
❌ Agile teams self‑organize. Trade‑offs should be handled collaboratively by the team and Product Owner using value‑based reasoning.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
4 Situational based Practice Tests : Agile Test Series
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram