PMP Question 659

Home Forums PMP Questions and Answers Discussion PMP Question 659

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #28535
    admin
    Keymaster

    You’re facilitating a strategic roadmap planning session. The Product Owner has prioritized features based on stakeholder pressure rather than customer impact or business value. Meanwhile, the team is concerned that high-value but less visible enablers are being delayed.

    What is the most appropriate action to take next?

    A. Proceed with current priorities to maintain stakeholder alignment
    B. Reprioritize based on Weighted Shortest Job First (WSJF) or similar value metrics
    C. Ask the team to push enablers in quietly alongside visible work
    D. Raise the concern in the next Sprint Review for broader input

    #28537
    admin
    Keymaster

    ✅ Correct Answer: B. Reprioritize based on Weighted Shortest Job First (WSJF) or similar value metrics

    🔍 Explanation of Options:
    A. Proceed with current priorities to maintain stakeholder alignment
    ❌ Incorrect. Agile prioritization should be based on customer and business value, not politics or pressure. This option sacrifices long-term outcomes for short-term comfort.

    B. Reprioritize based on WSJF or similar value metrics
    ✅ Correct. WSJF (or similar frameworks like MoSCoW or Value vs. Effort) helps make objective, transparent decisions. It ensures the most valuable work is done first.

    C. Ask the team to push enablers in quietly alongside visible work
    ❌ Incorrect. This bypasses proper prioritization and reduces transparency, which contradicts Agile principles.

    D. Raise the concern in the next Sprint Review for broader input
    ❌ Incorrect. Sprint Reviews are for inspecting the Increment, not for strategic roadmap prioritization. That should happen in roadmapping or portfolio sessions.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    4 Situational based Practice Tests : Agile Test Series

    PMP/Agile Useful Resources : PMP/Agile Resources

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.