✅ Correct Answer: B. Investigate if tasks are updated only near sprint end
🔍 Explanation:
A. Present the chart proudly during the review
❌ Wrong.
You’d be hiding a process flaw. The chart is misleading if it shows ideal progress but doesn’t reflect daily reality. Transparency is key in Agile.
B. Investigate if tasks are updated only near sprint end
✅ Correct.
This behavior is known as “burndown masking”—teams may delay updating tasks to avoid scrutiny. It undermines empirical process control and Agile inspection/adaptation.
C. Focus on meeting sprint goals, not chart accuracy
❌ Misleading logic.
Yes, sprint goals matter—but burndown charts are tools for transparency. If they’re misused, even good outcomes hide bad processes.
D. Switch to burnup chart to show scope creep
❌ Irrelevant distraction.
There’s no mention of scope change. Switching chart types won’t fix false reporting behavior.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
4 Situational based Practice Tests : Agile Test Series
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram