KeymasterYou’re the Scrum Master for a team in Sprint 6 of a critical release. Midway through the sprint, a team member raises a new risk: a recently updated API from an external provider might break integration features planned for next sprint, and possibly affect current sprint stories.
The team is fully committed to this sprint, and the Product Owner is hesitant to shift focus. However, ignoring this risk could result in major rework or failure in the next iteration.
What should the Scrum Master do?
A. Facilitate a quick discussion and create a spike to explore the risk
B. Add the risk to the RAID log and revisit it in the next sprint
C. Ask the Product Owner to cancel the sprint to address the risk
D. Advise the team to stay focused and bring it up in the reviewJuly 9, 2025 at 1:17 PM #28505admin
Keymaster✅ Correct Answer: A. Facilitate a quick discussion and create a spike to explore the risk
🔍 Explanation:
A. Facilitate a quick discussion and create a spike to explore the risk
✅ Correct.
In Agile, emerging risks are handled as soon as they surface. A spike (time-boxed investigation or research task) can be added to the current sprint if capacity allows or prioritized for the next sprint. Facilitating a conversation immediately helps the team assess impact and adapt without panic.B. Add the risk to the RAID log and revisit it in the next sprint
❌ Too passive.
Waiting until the next sprint to act on a high-impact, time-sensitive risk goes against Agile’s principle of responding to change quickly.C. Ask the Product Owner to cancel the sprint to address the risk
❌ Too drastic.
Cancelling a sprint is rare and only justified when the sprint goal becomes obsolete. The risk here can be managed within the current structure.D. Advise the team to stay focused and bring it up in the review
❌ Too late.
By the review, it may be too late to explore or mitigate the risk. Agile favors early feedback and fast inspection to avoid surprises.Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
4 Situational based Practice Tests : Agile Test Series
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge -
AuthorPosts
- You must be logged in to reply to this topic.