KeymasterYou are facilitating Sprint Planning for a new Scrum team. The Product Owner presents a clear, prioritized backlog, and the team begins selecting items for the sprint. Some developers feel uncertain about how much they can commit to, while others are ready to move forward. As Scrum Master, you guide the team to make a sustainable decision.
Which of the following best describes the purpose of Sprint Planning?
A. To estimate total hours and assign work to team members
B. To set a sprint goal and forecast work the team can deliver
C. To lock down scope so no changes occur during the sprint
D. To finalize product backlog priorities for upcoming releasesJuly 6, 2025 at 2:39 AM #28493admin
Keymaster✅ Correct Answer: B. To set a sprint goal and forecast work the team can deliver
🔍 Explanation:
A. To estimate total hours and assign work to team members
❌ Incorrect. Scrum teams self-organize; work is not assigned top-down. Estimating hours may occur, but it’s not the main focus of Sprint Planning.B. To set a sprint goal and forecast work the team can deliver
✅ Correct. Sprint Planning is used to define the Sprint Goal and for the team to forecast what they believe they can achieve based on capacity and past velocity.C. To lock down scope so no changes occur during the sprint
❌ Incorrect. While changes to the sprint backlog are discouraged once the sprint starts, flexibility exists as new understanding emerges. The sprint backlog is owned and managed by the team.D. To finalize product backlog priorities for upcoming releases
❌ Incorrect. That’s done in Backlog Refinement and Release Planning, not Sprint Planning. Sprint Planning focuses only on the current sprint.Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
4 Situational based Practice Tests : Agile Test Series
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge -
AuthorPosts
- You must be logged in to reply to this topic.