✅ Correct Answer: A. Coach stakeholders on the role of the Product Owner
🔍 Explanation:
A. Coach stakeholders on the role of the Product Owner
✅ Best first step. The Scrum Master should educate stakeholders about Agile roles and boundaries. This prevents future role violations and reinforces team discipline without confrontation.
B. Instruct developers to ignore direct stakeholder input
❌ Incorrect as a first step. This could damage stakeholder relationships and place developers in an uncomfortable position. Better to resolve the root cause first.
C. Escalate the issue to the project sponsor
❌ Incorrect. Escalation is a last resort. The Scrum Master should first use coaching and facilitation to resolve the issue.
D. Ask the Product Owner to document all stakeholder asks
✔️ Helpful later. Transparency is important, but documentation won’t prevent the bypassing behavior. Role clarity must come first.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
4 Situational based Practice Tests : Agile Test Series
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram