✅ Correct Answer: C. Add improvements to the product backlog
🔍 Explanation:
A. Rework the feature in the current sprint
❌ Incorrect. Sprints are timeboxed and not reopened. Work should be done in upcoming sprints based on prioritization.
B. Cancel the next sprint to resolve the issue
❌ Incorrect. Sprint cancellation is rare and drastic—used only when sprint goals are no longer valid. This is not one of those cases.
C. Add improvements to the product backlog
✅ Correct. In Agile, all feedback—even post-review—should go through the product backlog to be prioritized by the Product Owner and potentially included in future sprints.
D. Escalate the concern to senior management
❌ Incorrect. Agile teams are self-organizing. This is a routine feedback scenario that should be resolved within the team, not escalated unnecessarily.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
4 Situational based Practice Tests : Agile Test Series
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram
-
This reply was modified 8 months, 3 weeks ago by
admin.