✅ Correct Answer: D. Add it to the backlog for future prioritization
🔍 Explanation:
A. Add the feature to the current sprint immediately
❌ Incorrect. Once a sprint begins, the scope is fixed. Adding work mid-sprint disrupts team focus and violates Agile discipline.
B. Pause the sprint and begin a new sprint with the feature
❌ Incorrect. Cancelling or pausing a sprint is rare and only done under extreme circumstances, usually by the Product Owner—not for a single feature.
C. Reject the request and stay focused on sprint goals
❌ Incorrect. While maintaining sprint focus is important, outright rejection ignores product value and stakeholder collaboration. The correct Agile approach is to address it via backlog.
D. Add it to the backlog for future prioritization
✅ Correct. The proper Agile way is to place the item in the product backlog. It can then be prioritized for a future sprint based on business value and team capacity.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram