PMP Question 631

Home Forums PMP Questions and Answers Discussion PMP Question 631

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #28420
    admin
    Keymaster

    During a sprint, a team member notices a potential improvement in how tasks are handled. What should the team do?

    A. Wait until the project ends to share it
    B. Suggest it during the next sprint retrospective
    C. Escalate it to the project manager
    D. Ignore it and follow the current process

    #28421
    admin
    Keymaster

    ✅ Correct Answer: B. Suggest it during the next sprint retrospective

    🔍 Explanation:
    A. Wait until the project ends to share it
    ❌ Incorrect. Agile encourages continuous improvement, not waiting for project closure.

    B. Suggest it during the next sprint retrospective
    ✅ Correct. The sprint retrospective is the formal opportunity for the team to inspect and adapt processes, making it the right time to propose improvements.

    C. Escalate it to the project manager
    ❌ Incorrect. Agile teams are self-managing. Improvements should come from within the team, not through top-down escalation.

    D. Ignore it and follow the current process
    ❌ Incorrect. Agile values learning and improvement. Ignoring issues limits growth and efficiency.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.