✅ Correct Answer: B. Suggest it during the next sprint retrospective
🔍 Explanation:
A. Wait until the project ends to share it
❌ Incorrect. Agile encourages continuous improvement, not waiting for project closure.
B. Suggest it during the next sprint retrospective
✅ Correct. The sprint retrospective is the formal opportunity for the team to inspect and adapt processes, making it the right time to propose improvements.
C. Escalate it to the project manager
❌ Incorrect. Agile teams are self-managing. Improvements should come from within the team, not through top-down escalation.
D. Ignore it and follow the current process
❌ Incorrect. Agile values learning and improvement. Ignoring issues limits growth and efficiency.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram