    A project manager is new to Agile and insists on creating a detailed plan that must be followed strictly through the entire project. What is the best action to promote an Agile mindset?

    A. Support the plan to maintain consistency
    B. Recommend strict adherence to the plan
    C. Encourage flexibility and frequent feedback
    D. Ask the team to ignore the project manager

    #28414
    admin
    Keymaster

    ✅ Correct Answer: C. Encourage flexibility and frequent feedback

    🔍 Explanation:
    A. Support the plan to maintain consistency
    ❌ Incorrect. Agile does not aim for rigid consistency. It values adaptability over fixed planning.

    B. Recommend strict adherence to the plan
    ❌ Incorrect. Agile embraces change, especially when it delivers more value. This option reflects a traditional mindset, not Agile.

    C. Encourage flexibility and frequent feedback
    ✅ Correct. This promotes the Agile values of adaptability, learning, and collaboration—core to the Agile mindset.

    D. Ask the team to ignore the project manager
    ❌ Incorrect. Agile values respect and collaboration. Ignoring team members undermines trust and teamwork.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.