✅ Correct Answer: B. Log feedback and update the product backlog
🔍 Explanation:
A. Rework the feature before ending the sprint
❌ Incorrect. Sprint review is for feedback, not for making immediate changes. Changes should go through proper backlog prioritization.
B. Log feedback and update the product backlog
✅ Correct. Agile encourages gathering feedback during sprint reviews. Items that are no longer aligned with business goals can be added or updated in the product backlog for future sprints.
C. Escalate the issue to senior management
❌ Incorrect. Agile promotes self-managed teams. Not every misalignment needs escalation; the product owner manages feedback through the backlog.
D. Reject the feedback as the sprint is already complete
❌ Incorrect. Feedback is essential in Agile. Rejecting it goes against the principle of customer collaboration and continuous improvement
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram