Correct Answer is C. Cancel the sprint and re-plan with new priority
A. Swap a low-priority task with the compliance item
❌ Incorrect. Mid-sprint changes break the sprint’s stability and focus.
B. Ask the team to speed up current work
❌ Incorrect. Agile promotes sustainable pace and quality delivery.
C. Cancel the sprint and re-plan with new priority
✅ Correct. Sprint can be canceled if the goal becomes obsolete or invalid.
D. Reprioritize the backlog for the next sprint
❌ Incorrect. Delaying a critical compliance item risks non-compliance.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram