Home › Forums › PMP Questions and Answers Discussion › PMP Question 62 This topic has 1 reply, 1 voice, and was last updated 5 years ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts April 28, 2020 at 10:20 AM #5981 adminKeymaster All of the following statements about Work Breakdown Structure are TRUE except? a) Project manager creates it b) WBS prevents work from slippage through the cracks c) WBS provides a basis for estimating the project d) WBS helps to organize the work April 28, 2020 at 10:22 AM #5982 adminKeymaster The correct answer is A. Whole team helps in preparing the WBS. This has got additional benefit that it ensures team buy-in. Pass PMP in the First Attempt : PMP Strategy All PMP Question & Answers: Question & Answers Revise PMP Concepts: PMP Concepts PMP Tips & Tricks: PMP Tips & Tricks Quiz: 20 Questions Challenge 50 Questions Challenge PMP Agile based Quiz: 20 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In