    Which of the following techniques make sure our storypoint unit remains consistent for all our estimates over the duration of the project?

    A. Affinity Estimating
    B. T-Shirt Size estimating
    C. Planning Poker
    D. None of these

    #28289
    admin
    Keymaster

    Correct answer is A.

    Affinity Estimating ensures that our storypoint unit remains consistent for all our estimates over the duration of the project.