    The development team gathered to break user stories into tasks. The team is involved in which ceremony?

    A. Release Planning
    B. Iteration Planning
    C. Daily Stand-up
    D. None of the above

    #28279
    admin
    Keymaster

    Correct answer is B.

    In the iteration planning, team discuss user stories and breaks them into tasks at the last responsible moment. Tasks are the smallest chunks of work required to build the story.

    PMP/Agile Useful Resources : PMP/Agile Resources

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

    • This reply was modified 6 days, 9 hours ago by admin.
Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.