    An Agile team is in Sprint 5. Team selected 4 user stories for the sprint backlog. User story 1 constitute of 2 points, user story 2 constitute of 4 points, user story 3 constitute of 3 points and user story 4 constitute of 4 points. Team divided user story 4 into 2 equal tasks. By the end of Sprint 5, team completed user stories 1, 2, 3 and one task of user story 4. How many story points will contribute towards velocity in Sprint 5.

    a. 13
    b. 11
    c. 10
    d. 9

    #28222
    admin
    Keymaster

    Correct answer is D.
    Claim 1 Pi coin. 1 Pi = $38 on Forbes. Referral Code- behappiest

    In Scrum, only fully completed user stories contributes towards velocity. Since User Stories 1, 2, and 3 are completed, therefore, they will contribute towards velocity.

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

    • This reply was modified 11 months, 2 weeks ago by admin.
    • This reply was modified 11 months, 2 weeks ago by admin.
    • This reply was modified 11 months, 2 weeks ago by admin.
Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.