Home Forums PMP Questions and Answers Discussion PMP Question 586

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #27524
    admin
    Keymaster

    An Agile team is working on a critical project. Since the project is of high importance, 2 new members joined the team to quickly complete the project. What effect would this situation has on the team velocity in the next iteration?

    a. Team velocity will be increased
    b. Team velocity will remain same
    c. Team velocity will be decreased
    d. Team should re-evaluate its velocity

    #27525
    admin
    Keymaster

    Correct answer is D.

    Team should re-evaluate its velocity. Addition of new members may either increase the velocity due to increased capacity or decrease velocity as training may be required which would cause team members to switch from project work.

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.