    In the Burndown chart, line is 50 points above the projected line. What is the status of the project ?

    A. Behind schedule
    B. Ahead of schdule
    C. On time
    D. Data is insufficient to share schedule status

    #26634
    admin
    Keymaster

    Correct answer is A.

    In the Burndown graph, line shows how much work is pending. Since the actual progress line is above the projected line, therefore, it means more work is pending as per planned schedule.

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.