Correct answer is D.
Agile teams estimate their velocity for the first iteration not by guessing, but by deciding how many of the top-priority items in the backlog they can commit to completing in the first iteration. The total story points for these stories becomes their starting velocity estimate. Velocity from previous projects and other teams isn’t relevant, since velocity is unique to each team and project.