    Sara, an Agile Coach, was explaining the importance of Burn charts to the team. She explained how burn charts can be useful in tracking down team’s performance. Which of the following statements about burn charts is wrong?

    a. Burndown chart goes down whereas Burnup chart goes up
    b. Burndown chart shows remaining work whereas Burnup chart shows completed work
    c. Burndown chart shows scope changes whereas Burnup chart doesn’t
    d. Burndown chart doesn’t shows scope changes whereas Burnup chart shows it

    #23787
    admin
    Keymaster

    Correct answer is C.

    Burnup charts maps both total work and work completed. In case of scope changes, that work is reflected in the total work.

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.