Company ABC decided to execute Project XYZ through Kanban. Team leader was explaining how does Kanban works and helps in project execution. He explained the flow of work items in Kanban. Which of the following is correct?
a. All tasks are assigned to members in starting itself
b. Team leader assigns new task when members complete their task
c. When any task is completed new task is pulled from previous stage
d. Scrum Master assigns new task to the team members