Home › Forums › PMP Questions and Answers Discussion › PMP Question 56 This topic has 1 reply, 1 voice, and was last updated 1 year, 5 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts April 18, 2020 at 6:52 PM #5665 adminKeymaster In traditional project management, Project Manager is primarily responsible for Integration Management. In an Agile setting who is primarily responsible for integration management? A. Agile Team B. Product Owner C. Agile Coach D. Project Sponsor April 18, 2020 at 6:54 PM #5667 adminKeymaster Correct answer is A. In Agile, team members are responsible to put plans and components together. Pass PMP in the First Attempt : PMP Strategy All PMP Question & Answers: Question & Answers Revise PMP Concepts: PMP Concepts PMP Tips & Tricks: PMP Tips & Tricks Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In