    In traditional project management, Project Manager is primarily responsible for Integration Management. In an Agile setting who is primarily responsible for integration management?

    A. Agile Team
    B. Product Owner
    C. Agile Coach
    D. Project Sponsor

    #5667
    admin
    Keymaster

    Correct answer is A.

    In Agile, team members are responsible to put plans and components together.