    What will be the Agile approach to develop the requirement that is of High Value and Low Risk?

    A. Do First
    B. Do Second
    C. Do Later
    D. Do it when you want to get stakeholders support

    #5662
    admin
    Keymaster

    Correct answer is B

    As per Risk-Value Quadrant (Agile Requirements Prioritization Scheme)
    Do First – High Value and High Risk
    Do Second – High Value and Low Risk
    Do Third – Low Value and Low Risk
    Avoid – Low Value and High Risk

    Main point is high risk items need to be get off as early as possible because they can derail the whole project. If it is of low value we can ignore it. But if it is of high value then it should be done first so that if we fail then atleast we fail early to save time and effort.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.