    An Agile team is facing problem in delivering the work on time. Team wants to know the bottleneck activity which is causing the delay. Team divides the overall work in progress into individual activities and plot them in cumulative flow diagram. How can the team identify the bottleneck activity?

    a. Widening activity is the bottleneck activity
    b. Activity above the widening activity is the bottleneck activity
    c. Activity below the widening activity is the bottleneck activity
    d. Cumulative Flow Diagram cannot determine bottleneck activity

    #22672
    admin
    Keymaster

    Correct answer is C.

    Bottleneck is the activity that lies below the widening band. It is progressing at a slower rate than the widening activity.

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.