    An agile team wanted to improve its process. They used value stream map to check value adding and non-value adding activities. Earlier Value added time was 18 minutes and non-value added time was 36 minutes. After analysing scope of improvement, value added time was 18 minutes and non-value added time was 20 minutes. By what percentage process efficiency got increased?

    a. 33%
    b. 47%
    c. 14%
    d. 39%

    #22543
    admin
    Keymaster

    Correct answer is C.

    Earlier process efficiency = Value added time / Total Time = 18 / (18 + 36) = 33 %

    Now process efficiency = Value added time / Total Time = 18 / (18 + 20) = 47 %

    Imrpovement in Process Efficiency = 47% – 33% = 14%

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.