    Your project has a medium amount of risk and is not well defined. The sponsor hands you a project charter and asks you to confirm that the project can be completed within the project budget. What is the BEST method to handle this?

    a) Build the estimate in the form of range of possible results.
    b) Ask the team members to help estimate the cost based on the project charter.
    c) Based on the information you have, calculate a parametric estimate.
    d) Provide an analogous estimate based on past history

    #5598
    admin
    Keymaster

    Correct answer is a.

    Since it is early in the project and the detailed information is unavailable so it would be better to provide estimate in the form of ranges.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.