    During the upcoming release planning, Epics were decomposed into smaller stories and the summation of story points of smaller stories got decreased as compared to that of epic. What effect this will have on the Burndown chart?

    a. There will be no change
    b. Burndown graph will go up
    c. Burndown graph will go down
    d. Nothing can be concluded from this information

    #22168
    admin
    Keymaster

    Correct answer is C.

    Since the total number of story points got decreased after decomposing epic into smaller stories so burndown graph will go down.

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.