Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #3977
    admin
    Keymaster

    Many more changes are made during the project executing processes that had been expected. What is the BEST thing for the project manager to do now?

    a) Wait until all changes are known, print out a new schedule, and revise the baseline
    b) Make changes as needed, but maintain schedule baseline
    c) Make only the changes approved by the management
    d) Talk to management before any changes are made

    #3978
    admin
    Keymaster

    The correct answer is B.

    The schedule baseline is there for you to determine how the project is progressing. Follow your change management process, and continue to track against your baseline.

    Pass PMP in the First Attempt : PMP Strategy

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.