    Generally on an Agile project, who can provide the best estimation of the tasks?

    a. Development Team
    b. Product Owner
    c. Scrum Master
    d. Subject Matter Expert

    #12953
    admin
    Keymaster

    Correct answer is A.

    Since Development Team executes tasks so they are the closest to the technical details of the project. They can best provide the estimation regarding size and time required to complete the tasks.

    Post queries : Queries

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

    #13332
    Hamiti
    Guest

    I m agree

Viewing 3 posts - 1 through 3 (of 3 total)
  • You must be logged in to reply to this topic.