    An Agile team faced critical security issue in their ongoing project. Similar issue was faced by the company in the other project in the past. What approach should the team follow in this situation?

    a. As all projects are unique so the team should work on new solution from the scratch to cover all scenarios
    b. Team should reuse the solution implemented in the other project and make necessary changes
    c. Team should outsource the solution and continue to work on other parts of the project
    d. Team should park the issue and handle it later, if its probability or impact increases

    #12934
    admin
    Keymaster

    Correct answer is B.

    Alistair Cockburn has defined success strategies in which one of the strategy is copy and alter. This helps in having a working framework to start with and avoids blank page syndrome.

    Post queries : Queries

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.