    In terms of Lean, which of the following is not the form of waste?

    a. Requirement specification waiting for development
    b. Team members assigned to other projects
    c. Waiting for development manager approval to start development
    d. Creating overall document in French, apart from English, for legal approval

    #12137
    admin
    Keymaster

    Correct answer is D.

    In Lean and Agile, documentation is just enough, just in time and whenever it is necessary. In the present case, for legal approval, document has to be in French language, otherwise our product cannot be approved. Therefore, it is necessary and not the form of waste.

    Post queries : Queries

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.