    A new employee of the company is assigned to work on a project that is in the early planning processes. She has to decide today if she will accept the assignment to the project or whether she wants to be assigned to a different project. however, the project manager is not at work and is not reachable. Where can the team member look to help her determine what work she is given on the project?

    a) Activity definitions
    b) Project management plan
    c) Job Descriptions
    d) Responsibility Assignment Matrix

    #5468
    admin
    Keymaster

    The correct answer is D.

    Job description describes her primary job and not the responsibilities on the project. Responsibility assignment matrix describes her responsibilities on the project.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.