    A new project manager has just been assigned a project that is in progress and is two weeks behind schedule. The team members are about to be distributed to another project based on the original time estimates by the functional manager. What kind of organization is the new Project Manager in?

    a) Projectized
    b) Tight Matrix
    c) Balanced Matrix
    d) Functional

    #5456
    admin
    Keymaster

    Correct answer is d.

    Project Manager has less authority, therefore, it is functional type of organization.