    An agile team has successfully completed the retrospective process. The facilitator wants to know how the session went. Which of the following technique can help him to gather feedback about retrospective process?

    a. ROTI
    b. ROI
    c. Plus/Delta
    d. SMART goals

    #11927
    admin
    Keymaster

    Correct answer is A.

    ROTI stands for Return on Time Invested. It is used during the closing phase of the retrospective process to know about the effectiveness of the retrospective session.

    Post queries : Queries

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.