    You join as a Scrum Master to new Scrum Team; you notice that the Product Owner and the Development Team are spending too much time in the product backlog refinement. You discovered that the team is detailing information for all the user stories in the product backlog. How would you address this issue?

    A) Do nothing as the team discovered that refinement is very valuable to them
    B) Ask product owner to take the responsibility of refining the backlog items and let the Development Team focus on current sprint goals
    C) Cancel all refinement meetings until team start meeting commitments
    D) Coach team members to spend just enough time to refine the backlog for upcoming Sprint.

    #11774
    admin
    Keymaster

    Correct answer is D.

    In agile, team follows progressive elaboration. In this, we refine only those items in detail that we are going to do next or in near future.

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.