    During earlier stages of one of the project, sponsor hands you high level requirements and asks you to confirm if the project can be completed within the project budget. What is the BEST method to handle this?

    a) Build the estimate in the form of range of possible results.
    b) Ask the team members to help estimate the cost based on the high level requirements.
    c) Based on the information you have, calculate a parametric estimate.
    d) Provide an analogous estimate based on past history

    #11720
    admin
    Keymaster

    Correct answer is a.

    Since it is early in the project and the detailed information is unavailable so it would be better to provide estimate in the form of ranges.

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.