  • #5264
    admin
    Keymaster

    A project manager received executive orders to deliver the project two weeks earlier than scheduled, doing whatever it takes. He decided that the least costly means would be to add resources to critical path activities in order to shorten the time of those activities in this case, the project manager has?

    a) Fast tracked the critical path part of project schedule
    b) Decomposed the critical path WBS
    c) Leveled resources
    d) Crashed the critical path

    #5265
    admin
    Keymaster

    The correct answer is D.

    Crashing is the technique used to shorten the schedule duration for the least incremental cost by adding resources.