During the identification of risks on your project, you have determined that there is a very high probability of conflict among the team during project executing over one aspect of the final design of the project. Which of the following is an example of mitigating the impact of risk to the project?
a) Obtain an insurance policy for the anticipated cost of the impact
b) Provide the team with training on conflict resolution techniques
c) Outsource that part of the project to another company
d) Eliminate that part of the project