    An agile team wanted to improve its process. They used value stream map to check value adding and non-value adding activities. Earlier Value added time was 18 minutes and non-value added time was 18 minutes. After analysing scope of improvement, value added time was 18 minutes and non-value added time was 9 minutes. By what percentage process efficiency got increased?

    a. 50%
    b. 67%
    c. 17%
    d. 57%

    #11217
    admin
    Keymaster

    Correct answer is C.

    Earlier process efficiency = Value added time / Total Time = 18 / (18 + 18) = 50 %

    Now process efficiency = Value added time / Total Time = 18 / (18 + 9) = 67 %

    Tips/Tricks/Cheat sheet to master PMP Exam and Concepts : PMP Tricks/Tips/Cheat sheet

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.