PMP Question 362

Home Forums PMP Questions and Answers Discussion PMP Question 362

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #11127
    admin
    Keymaster

    Maria, Product Owner, with the help to development team prepares the list of risky items. Maria just begin the role of Product Owner. She approached Sara, Scrum Master, on how to manage risky items. What Sara should recommend to Maria?

    a. Wait till more information becomes available
    b. Implement risky items as early as possible
    c. In any given iteration there should be mixture of risky and non-risky items
    d. Delay the implementation of risky items so that if information comes not to implement it then drop those items.

    #11128
    admin
    Keymaster

    Correct answer is B.

    In Agile, risky items should be implemented as early as possible. This helps to address riskier items early in the project and if in case it is not possible to implement it then we can conclude early whether to proceed with the project or not.

    Learn PM concepts through daily life experiences : PM Video Tutorials

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.