    In the retrospective meeting, team discussed few measures to reduce the build time from 10 minutes to 5 minutes. They found that a particular module takes more time and decided to refactor it to improve build time. Team had done such improvements in the past. When the team shared this with Product Owner, product owner asked to implement it in future iterations. What is the problem with this goal?

    a. It is not specific
    b. It is not measurable
    c. It is not attainable
    d. It is not time bounded

    #11091
    admin
    Keymaster

    Correct answer is D.

    There is no specified time within which the target is to be achieved.

    Learn PM concepts through daily life experiences : PM Video Tutorials

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.