    During the first iteration, the team estimated to complete 5 user stories. Development part of each user story is estimated at 3 story points and testing part is estimated at 2 story points. By the end of the iteration, team developed and tested 4 user stories and developed the fifth user story but could not test it. What was your team’s velocity for the first iteration?

    a. 15
    b. 20
    c. 23
    d. 25

    #11071
    admin
    Keymaster

    Correct answer is B.

    In Agile, velocity is calculated on basis of completed user stories. Impartial work doesn’t contribute towards the velocity.

    Learn PM concepts through daily life experiences : PM Video Tutorials

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.