    An activity needs more time because an identified risk has occurred. The project manager determines that there is enough reserve to accommodate the change. Who needs to approve the change?

    a) Management
    b) Project manager
    c) Team Member
    d) Functional Manager

    #4886
    admin
    Keymaster

    The correct answer is B.

    It is the project manager’s responsibility to manage the project scope completion within budget and reserves.