PMP Question 348

Home Forums PMP Questions and Answers Discussion PMP Question 348

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #11055
    admin
    Keymaster

    Maria, Scrum Master, got to know from few people in the organization that the current project will no longer deliver the value that it was intended to deliver when it got started. What should Maria do in such situation?

    a. Cancel the project
    b. Check what all projects her team members will be assigned next
    c. Ask Product Owner if the team still needs to work upon the project
    d. Help team members by providing the information and asking them to explore opportunities

    #11056
    admin
    Keymaster

    Correct answer is C.

    Product Owner is the right person who can make decision if the team has to continue working upon the project or the project has to be cancelled.

    Learn PM concepts through daily life experiences : PM Video Tutorials

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.