    Agile team recently finished the iteration review and is conducting the retrospective session. Maria, scrum master, wants to know if the retrospective session is going well and improvements for future sessions. Which of the following technique would help Maria in such situation?

    a. Helped, Hindered, Hypothesis
    b. Plus/Delta
    c. Short Goals
    d. ROTI

    #11033
    admin
    Keymaster

    Correct answer is A.

    Helped, Hindered, Hypothesis helps to get feedback about retrospective – what helped, what hindered and how retrospectives can be improved in future.

    Learn PM concepts through daily life experiences : PM Video Tutorials

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.