PMP Question 344

Home Forums PMP Questions and Answers Discussion PMP Question 344

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #11021
    admin
    Keymaster

    Sara is working as the scrum master for her team. During her absence, senior management asked team about the current project schedule and future plans. Team prepared detailed task status and plans and shared with the senior management. Senior Management liked it very much and asked team to share these reports on regular basis. Sara got to know about it when she joined back. What should she do in such scenario?

    a. Appreciate the team and continue reporting the same way as senior management liked it
    b. Discuss with senior management and revoke the detailed plans
    c. Track team performance against the plan and make necessary changes
    d. Display the detailed plan to the whole team so that everyone is aware of the status

    #11023
    admin
    Keymaster

    Correct answer is B.

    Agile projects are change-driven. They do not follow detailed plans. Having detailed plans restrict agility and restrict necessary changes required.

    Learn PM concepts through daily life experiences : PM Video Tutorials

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.