The project deadline is the end of the year, the project consists of 2 activities. Activity A has a duration of 2 months and activity B has a duration of 3 months. Activity A nad B can be performed concurrently. The start date for the project is set for the beginning of July. What is the MAXIMUM duration of the project?
Did you get tricked into looking at the length of each activity to calculate project length? The start is the beginning of July and the end is the end of the year, making the maximum duration six months.