A scope change is made on the project. You have determined the effects on the schedule, perform integrated change control, and adjusted the project baselines and the project management plan. What is the NEXT thing to do?
a) Look for impacts to cost
b) Notify stakeholders affected by change
c) Submit the change to the change control board for approval
d) Change the work breakdown structure
Integrated change control includes looking for impacts to cost (choice A). Submitting the change to the change control board (choice C) would have been done before the baselines and plans were adjusted. Adjusting the project management plan implies that the work breakdown structure (choice D) would have been updated as well. Many people forget to notify stakeholders of changes and how the changes will affect them. Choice B is important, and the best answer here.