Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #4805
    admin
    Keymaster

    Halfway through the executing processes of your project, a team member alerts you to a potential cost overrun for a specific deliverable. What do you do FIRST?

    a) Determine the projected actual cost
    b) Implement a change control process to track the change
    c) Inform the customer
    d) Determine the cause of the overage

    #4806
    admin
    Keymaster

    The correct answer is D.

    A project manager must always evaluate the situation before making a decision.

    Pass PMP in the First Attempt : PMP Strategy

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.