A project manager is trying to settle a dispute b/w two team members. One says the systems should be integrated before testing, and the other maintains each system should be tested before integration. The project involves over 30 people, and 12 systems need to be integrated. The sponsor is demanding that integration happens on time. What is the best statement the project manager can make to resolve the conflict?
a) Do it my way
b) Lets calm down and get the job done
c) Lets deal with this gain next week after we all calm down
d) Let’s do limited testing before integration and final testing after integration